Wondering What an "Impacted Schedule" Is?

David Murphy

According to materials from Metro’s January Construction Committee meeting agenda, Kiewit recently submitted an “Impacted Schedule” forecasting an additional 9 month delay. Wondering what an “impacted schedule” is? Here is the relevent language from Metro’s contract with Kiewit:

[SEC 3.4] (b) Impacted Schedule. — To the extent that there are pending Modifications (including Change Orders, known delays, and claims for delays) that may affect the Critical Path Schedule, the Design Builder shall submit an adjusted Critical Path Schedule, as impacted by all such pending Modifications, representing its best estimate of actual performance (“Current CPM Contract Schedule Updates”). The Design Builder shall submit the impacted schedule without regard to whether the pending Modification has been recognized or accepted.